CPD Zone
Main Menu
Mini Guides
Recommended Articles
Repudiation – damages Print
There are two elementary principles that apply when assessing damages for a breach of contract. Firstly, the damages should put the claimant in the same position as if the contract had never been performed (ie compensate him fully for his losses). Secondly, the quantum of damages should be assessed as at the date of breach.

But, what happens when those two principles are in conflict? This point was recently address by the HL in an important decision involving a contract that had been repudiated. A ship had been chartered for a fixed period until 2005. However, the hirer returned the ship early (in 2001), so repudiating the contract. The owner of the ship accepted that repudiation, and the question then arose as to the damages that should be payable. That issue was made more complicated, however, by the outbreak of the Iraq War in 2003 which would have brought the charter arrangement to an automatic end (the charter agreement contained a standard clause allowing either side to cancel the contract if the UK, US, or certain other countries went to war). On that basis, the hirer argued that damages should be limited to the period to 2001 to 2003. Against that, the owner argued that damages should be assessed as at the time of the breach and so cover the period 2001 to 2005.

Surprisingly, there has never been a senior authority on this point. The HL came out in favour of the hirer, taking the view that it was more important to achieve ‘an accurate assessment of the damages based on the loss actually incurred’. Thus, post-repudiation events (ie the Iraq War) could be taken into account in assessing the damages – which were not to be assessed solely as at the date of repudiation.

As a note from practicallaw.com points out, this case is potentially of significance within the property sector (eg where T hands back a property before the expiry of a lease). It opens up the possibility of T being able to argue that post-repudiation events might affect the quantum of damages due to L (ie it should be less than the mere balance of rent due). However, the caveat to that is that the charter agreement in this case specifically contemplated the possibility of war (ie a war risks clause) and that was the post-repudiation event taken into account by the HL; accordingly, the case is not authority for saying that other events not contemplated by the parties can be taken into account. But, if there is a clause in the lease (eg destruction by fire clause) then logic would seem to dictate that such a clause could be taken into account when assessing damages to be paid by a repudiating T.

Golden Strait v Nippon [2007] UKHL 12. Source: www.practicallaw.com (subscription service). © Practical Lawyer

April 2007
Username:

Password:


Subscribe now
Case Links
advertisement

Exchange/
completion Weblinks



What's on this site | Contact us | Terms & Conditions | My Account