|
Andrew Annette reviews the court’s findings in a recent
case involving a delay by a landowner in enforcing a
restrictive covenant
It does not automatically follow that a
delay in objecting to a breach of
restrictive covenant amounts to an
acquiescence to that breach. In the case of
Harris v Williams-Wynne [2006] the Court
of Appeal, in upholding the decision
of the High Court, decided that a
landowner that delayed in objecting to a
breach of covenant was nevertheless entitled
to claim damages for that breach.
However, as the landowner found out,
the level of damages awarded will not
necessarily reflect the profit made by the
developer by that breach.
Background
In April 1987 Mr Harris purchased from
Mr Williams-Wynne a farmhouse in the
Snowdonia National Park. Shortly after
arriving, Mr Harris sought to purchase
more land from Mr Williams-Wynne,
who entered into a contract in April 1988
(the agreement) to sell some additional
amenity land adjacent to the farmhouse
(the additional land) to Mr Harris, which
contained the following covenants:
2. The vendor… undertakes that if notice in
writing is given to the vendor within
twenty one years from the date hereof the
vendor at the Purchaser’s expense will execute
any document required to transfer the
said freehold interest in such land to the
Purchaser or as the Purchaser may direct
and use his best endeavours to obtain the
concurrence of any necessary party.
3 The Purchaser… in view of the land
being within a National Park covenants
for the benefit of the vendor’s retained
land not to erect any buildings on the
land the subject of this agreement.
It was somewhat unusual that
Mr Harris did not take a transfer of the
additional land but instead relied on a
contractual right to purchase.
The breach of covenant
In 1991 Mr Harris obtained a planning
consent for the erection of a two-storey
garage and studio on the additional
land. In 1995 Mr Harris began implementing
the planning consent by
removing an existing garage on the
additional land and commenced building
works for the garage and studio with
foundations being installed in 1997.
Works continued in a rather ad hoc fashion.
By the spring of 2000 the building
had reached first-floor level and by
December 2002 the roof had been
installed and slated.
In 2002 Mr Harris decided to sell
the farmhouse garage and studio.
During the conveyancing process it
was soon pointed out to Mr Harris that
he did not in fact own the additional
land. In December 2002 Mr Harris’s solicitors
formally contacted Mr Williams-
Wynne requesting the transfer of the
additional land. This request was
ignored. Some five months later, Mr
Williams-Wynne did respond by claiming
that Mr Harris had, by erecting the
garage and studio, breached the absolute
prohibition on building on the additional
land. Mr Harris sought specific performance
of the transfer claiming that he was
suffering financial loss as a result of
Mr Williams-Wynne’s failure to transfer
the land promptly when requested
In turn, Mr Williams-Wynne counterclaimed
for breach of covenant and
sought half the development profit.
In the proceedings that followed
it was conceded that Mr Williams-
Wynne would have become aware of the
building work on the additional land
during 2000. Mr Williams-Wynne did not live that far away from the building
being erected and it could be seen
from many points including the main
road. Mr William-Wynne often enjoyed
flying light aircraft over the area taking
aerial photos! The issue at the crux
of this case was whether the delay
would be fatal to any attempt by
Mr Williams-Wynne to enforce the
restrictive covenant.
Remedies available for
breach of covenant
Injunctive relief
It has generally been accepted by the
courts that an injunction is the natural
remedy for a breach of restrictive
covenant. However, the importance of a
landowner acting quickly if they wish to
obtain injunctive relief is highlighted by
the fact that a court is more likely to
grant a prohibitory injunction restraining
any anticipated breach of covenant
rather than a mandatory injunction
requiring the breach to be rectified (ie
by the pulling down of a building
erected in breach of covenant). Time is
very much of the essence when seeking
injunctive relief.
Damages
At common law the damages for a
breach of covenant are likely to be nominal
as it is difficult to establish actual
damage to the land (Surrey County
Council v Bredero Homes Ltd [1993]).
However, in equity more substantial
damages can be awarded under s2 of
the Chancery Amendment Act 1858
(Lord Cairns’ Act), provided the court
has jurisdiction to entertain an application
for an injunction (this is regardless
of whether a party actually seeks
an injunction or whether the court
feels an injunction is an appropriate
remedy).
Thus, provided the court feels it has
jurisdiction to grant an injunction, it will
consider whether damages would be a
more appropriate remedy. Using the
principles set down in Jaggard v Sawyer [1995] the court will consider whether it
can be shown that the likely injury
caused to any claimant by a breach of
covenant would be small, whether the
breach can be assessed in monetary
terms, whether a monetary payment is
adequate compensation, and whether
an injunction would be oppressive.
If the court feels that damages would
be a more appropriate remedy it
will begin its assessment of the level of damages as being such a sum as
the landowner may have reasonably
demanded as a quid pro quo for releasing/
varying the covenants had the
developer applied for them to be
released/varied (Wrotham Park v
Parkside Homes [1974]). In Amec
Developments Ltd v Jury Hotel
Management (UK) Plc [2001] the court
held that damages should be calculated
on the basis of a sum that would have
been negotiated between the parties
making reasonable use of their bargaining
positions at the time prior to the
breach of covenant, although it did
caveat this by stating that the ‘deal has
to feel right’. However, the courts are
also at liberty to award restitutionary
damages rather than compensatory
damages where such a reward would be
a ‘just response to a breach of contract’
(Attorney General v Blake [2001]).
Remedies available where
there has been delay
In some circumstances the courts have
ruled that injunctive relief is simply not
available. In Gafford v Graham [1999] the
court stated that a claimant who stands
by while a permanent and substantial
structure is erected in breach of covenant
loses the right to seek an injunction to
have that structure pulled down. In addition,
a landowner seeking damages for
breach of covenant may lose its entitlement
to claim damages where it has been
guilty of such acquiescence as to make it,
in all the circumstances, unconscionable
for it to rely upon this legal right (Gafford
v Graham).
It was therefore clear from the beginning
that in the case of Harris v
Williams-Wynne, the delay in seeking to
enforce the breach of covenant cost
Mr Williams-Wynne any chance of
obtaining a mandatory injunction. An
injunction so late in the day would
simply have been oppressive. To be fair,
Mr Williams-Wynne never really asked
for injunctive relief. The question for the
court was whether the delay meant that
Mr Williams-Wynne lost his right to
seek damages from Mr Harris.
The decision
Counsel for Mr Harris argued that the
delay was clearly an acquiescence to
the breach and, following Gafford v
Graham, argued that, in all the circumstances,
it would be unconscionable
for Mr Williams-Wynn to rely upon
the right to damages. Counsel for
Mr Williams-Wynne countered, arguing
that acquiescence required an encouragement
or allowance by Mr Williams-
Wynne and it was not sufficient
merely to establish a delay in making a
complaint.
Bernard Livesey QC, sitting in the
High Court, decided that it was relevant
to determine the extent to which any
delay on the part of Mr Williams-Wynne
had caused Mr Harris to act to his
detriment. The answer to this question
depended first on the conduct of Mr
Williams-Wynne, and secondly on the
wording of the covenant. In Mr Williams-
Wynne’s favour was the fact that the
covenant was an absolute prohibition on
building on the land. Counting against
him was, of course, his delay.
The judge concluded that the inactivity
of Mr Williams-Wynne was not fatal
to his claim for damages. Mr Harris had
profited from the construction of the
building, which had enhanced the value
of his land significantly and to an extent
greater than he would have paid for the
release of the covenant. Thus payment of
a proper sum for the breach of covenant
was not a ‘detriment’ that was unconscionable
for Mr Williams-Wynne to raise
at the stage at which he did.
The High Court awarded damages to
Mr Williams-Wynne, though it was not
the half of the development profit sought,
but instead £8,000. This was something of
a hollow victory as Mr Harris was
awarded damages for Mr Williams-
Wynne’s breach of contract for failing to
transfer the land when requested.
The appeal
Mr Harris appealed the High Court
decision, arguing that the award for
damages was incorrect in law as Mr
Williams-Wynne had acquiesced to the
construction of the building on the additional
land and was therefore not entitled
to damages. The Court of Appeal upheld
the decision and the reasoning of the
High Court in every respect.
Conclusion
Whilst in the circumstances of this case
Mr Williams-Wynne’s delay was not
seen as an acquiescence and thus he was
entitled to damages, the court was conservative
in the award made. Certainly,
the award was not the amount claimed
by Mr Williams-Wynne and developers
should take continued cheer from the
fact that the courts have, to a large extent,
ignored the precedent set by Attorney
General v Blake when dealing with damages
for breaches of restrictive covenants.
Finally, it is worth practitioners
remembering the purpose of the imposition
of restrictive covenants, especially in
the drafting of the same in sale contracts
and transfers. If the purpose of a
covenant is to secure amenity then it is
worth pointing out to the landowner benefiting
from the covenant that prompt
action on their part is vital if there is to be
any chance of securing that amenity. If,
on the other hand, the purpose of the
restrictive covenant is to secure future
development profit, practitioners are well
advised that such future profit may well
be better secured by a form of specified
overage as opposed to relying on the benefit
of a restrictive covenant.
|